Last week, I noted how the connection under Eisenhower Ave at Cameron Run was open. Spoke too soon...the fencing seen in the photo has been draped back across the trail. According to the city's bike-ped coordinator, the contractor still has a few things to finish on the punch-list.
Meanwhile, the Telegraph Rd connection across the Beltway is still closed...it's now been 2.5 weeks since VDOT briefed the Transportation Commission that it'd be open in 1 week. Time for an E-mail.
One more trail bit: Alexandria hopes to have the Chambliss Crossing project out to bid in a couple months. The 90% design plans were recently posted to the project website.